G'day,
The hulls are more or less completed (see photos in the photo section), but cannot be finished until we know the mast and beam specs. The rudder shafts are built. The rig and beams are waiting for the engineering to be completed and for the carbon to arrive. The carbon has been delayed and will not be here till next month. October launching won't happen, nor will Sydney Hobart this year. Still aiming for solo Transpac next year, but I have some ill family in the UK which may necessitate a month there round Xmas, which is prime building time.
So, unusually for me :-) the schedule has been blown away, and i am not sure what will happen, nor when.
regards,
Rob
Rob,
Any updates on Soliatarry?
Phil