Subject: [harryproa] Re: building 15m visionarry
From: "kenscherf" <kens-2007@hotmail.com>
Date: 11/25/2012, 9:03 PM
To: harryproa@yahoogroups.com.au
Reply-to:
harryproa@yahoogroups.com.au

 

Hi Rob,
I am having the beams, rudders, schooner rigs built by Rob Denney's engineer & building the rest. The plan is to build to bareboat stage in a shed & finish the fitout on the water. To bareboat stage should take around 6 months using the infusion method.
ken

--- In harryproa@yahoogroups.com.au, "rob_rassy" <techsmart@...> wrote:
>
>
> Hi Ken
>
> I'm not looking for a shed but am wondering how long you expect your
> build to take. Are you doing the complete build on the water or just the
> assembly?
>
> Rob Rassy
> --- In harryproa@yahoogroups.com.au, "kenscherf" <kens-2007@> wrote:
> >
> > Hi all,
> > Will be building early next year on the gold coast, australia and was
> wondering if there is anybody interested in sharing rental costs of a
> warehouse. To find one on the water would be looking at about $100 to
> $140 a day making it +-$60/day.
> > Ken
> >
>